The project to forever eliminate parking on the Overton Park Greensward got $3 million in federal funding Wednesday.
The U.S. House passed six spending bills Wednesday totaling more than $400 billion. Some of that money includes discretionary spending for projects all over the country, including the $3 million to further the Overton Park parking plan.
U.S. Rep. Steve Cohen announced the funding Thursday morning, noting that he voted for the bill that includes it. Cohen said the bill includes more than $17 million for Memphis projects, including $4 million for the renovation of the historic cobblestones at the river’s edge Downtown.
The new Overton Park parking plan was announced in March (more at the link below). It came after decades of complaints about Greensward parking, testy debates during Memphis City Hall meetings, a mediation process that ended at an impasse, a compromise plan that would have taken some acres from the Greensward, a hopeful new plan that would have built a parking deck on Prentiss Place and left the Greensward intact, and then the removal of that proposal after it proved too costly in favor of the previous compromise plan that would remove part of the Greensward.
The new plan preserves the entirety of the Greensward, restores 17 acres of parkland that has stood unused behind chainlink fences, swaps land between the park and the Memphis Zoo, and forever ends the zoo’s use of the Greensward for overflow parking.
Much work is to be done before that happens, though, said Tina Sullivan, executive director of the Overton Park Conservancy (OPC), which oversees the park for the city. The $3 million, she said, will help that work get done, make for quality work, and, maybe, get that work done more quickly.
Memphis Flyer: How big of a deal is this federal funding to the project?
Tina Sullivan: This is a huge deal. We knew we had this wonderful solution in hand and we knew we had the support of stakeholders on both sides and the city of Memphis. But we also knew it was going to cost a lot to implement, and that was gonna require everyone to go out and raise more money. Congressman Cohen delivered in getting this to sail through the House process.
I know there is still work to be done, and that we have a little bit more to go before it’s completely finalized, but this allows us to implement a better solution in a shorter timeframe than we would have. This will allow us to have a high-quality result on every piece of property that we’re going to touch with it.
What needs to be done?
TS: The project moves the zoo maintenance facility over to that southeast corner [of Overton Park] and allows the zoo to repave that current maintenance area [current home of the city’s General Services facility] for members parking.
There’s a lot of work that needs to be done in that southeast corner to make it ready for the zoo to move in and make it ready for the Conservancy to move in to the Southern portion of that. There is a lot of work to be done on the zoo’s current maintenance area demolishing buildings and designing a new parking lot over there.
A lot of work needs to be done on the Greensward. We’re going to need to remediate the Greensward. Our vision is to have some sort of permanent barrier between the zoo parking lot and the rest of the park. So, I think the “berm” that was discussed in our early negotiations, that may soften into something that’s a visual and a physical barrier, but maybe not. Maybe it’ll be something a little more appropriate to the design of the park. So, that still needs to be designed and then implemented.
Then, finally, part of this solution includes reclaiming that 17-acre tract of forest that’s been behind the zoo fence since for a couple of decades, at least. So, the zoo’s gonna need to move its exhibit space out from behind Rainbow Lake. And we need to take that big, chainlink fence down and move it over to establish a new zoo boundary in the forest. From there, we’ll have we’ll have some work to do in the forest, like invasive [plant] removal.
There is a large amount of work yet to be done. That’s going to cost a lot of money.